CCMP practice question 8 of 25
Who is responsible for ensuring the outputs of the lessons learned session are applied to future change projects?
Full set: 150 questionsThe change management lead is responsible for the stewardship and continuous improvement of the organization's change management practice. A critical component of this responsibility is capturing lessons learned from completed projects and ensuring they are integrated into the methodology, tools, and processes for future initiatives. This function is central to maturing the organization's overall change capability and ensuring past successes and failures inform future strategies. The lead acts as the custodian of the change management process itself.
A. A project team member's responsibility is typically confined to their specific tasks within a single project, not ensuring cross-project application of lessons learned.
B. The project sponsor is accountable for the success of their specific project; their role typically concludes with the project and does not extend to process ownership for future changes.
C. An external party may facilitate a lessons learned session for objectivity but lacks the ongoing authority and organizational role to ensure the application of findings in the future.
1. The Standard for Change Management (First Edition). Association of Change Management Professionals (ACMP), 2014.
Section 5.5, "Assess Change Management Performance," p. 101: This section states, "The purpose of this activity is to review the performance of the change management activities and the change management team to identify lessons learned and provide input for improving the performance of change management on future initiatives." The Change Management Lead is responsible for executing this process group.
Appendix B, "Roles in Change Management," p. 120: The description of the Change Management Practitioner/Lead outlines their responsibility for "applying a structured approach to change management." This implies ownership of the process and its continuous improvement through mechanisms like lessons learned.
Section 2.2, "Defining the Change Management Process," p. 20: This section emphasizes the value of a consistent and repeatable process. The Change Management Lead is responsible for maintaining and improving this process, which is achieved by institutionalizing lessons learned.
Keep practicing
Take the free CCMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CCMP practice questions
- Question 1What is the main purpose of assessing how well new change initiatives are aligned to the …
- Question 2What is the most significant element to look for when conducting an assessment of an orga…
- Question 3What document should provide guidance and best practices for future change initiatives?
- Question 4What is a recommended practice for aligning stakeholders around benefits and value of a c…
- Question 5What could be a significant input to the analysis of change objectives and in defining ne…
- Question 6The first two weeks of a large and complex change project is underway and things seem to …