A management review repeatedly identifies overdue high-risk recommendations but assigns no resources or accountability. What does this indicate?
Full set: 110 questionsThe purpose of a management review is to assess the performance of the process safety management system and to identify opportunities for improvement. When a review repeatedly identifies the same high-risk deficiencies (overdue recommendations) without allocating the necessary resources or assigning clear accountability for correction, it demonstrates a fundamental breakdown in the management system. The "review" step is occurring, but the "act" step of the Plan-Do-Check-Act cycle is failing. This signifies a failure to translate findings into tangible actions, rendering the review process ineffective and undermining the organization's safety culture.
A. This describes the opposite of the situation; an effective loop would ensure recommendations are addressed and closed, demonstrating continuous improvement.
B. A lack of action on high-risk items indicates a deficiency in safety management or culture, not an excess of process knowledge.
C. Contractor prequalification is a separate process safety element and is not directly related to the failure of an internal management review loop.
1. Center for Chemical Process Safety (CCPS). (2007). Guidelines for Risk Based Process Safety. AIChE.
Chapter 20, Management Review, Section 20.1, "Element Overview," p. 447, states the objective is to "ensure that the RBPS management system remains suitable...and to identify actions to improve its effectiveness." A failure to act on findings directly contradicts this objective.
2. Mannan, S. (Ed.). (2012). Lees' Loss Prevention in the Process Industries (4th ed.). Butterworth-Heinemann.
Chapter 19, "Management of Safety," Section 19.5.4, "Management review," emphasizes that reviews must lead to "decisions and actions related to the improvement of the effectiveness of the OHSMS [Occupational Health and Safety Management System]."
Keep practicing
Take the free CCPSC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CCPSC practice questions
- Question 1Which characteristics must a protection layer generally have to receive full independent …
- Question 2An operator repeatedly uses a handwritten startup checklist that differs from the approve…
- Question 3Which of the following are evidence that good workforce involvement exists at a facility?…
- Question 4Which information should an operating procedure include for a critical process step? (Sel…
- Question 5Who is involved in Management Review at an operating facility? (select all that apply)
- Question 6The Risk Based Process Safety element which is designed to verify that a process is verif…