CFI-I practice question 2 of 35

When submitting materials for plan review, the applicant has the responsibility to ensure I . That construction documents include all of the fire protection requirements. II . That shop drawings are correct and in compliance with applicable codes and standards. III . That all contracts are in place.

Full set: 100 questions
Answer options
A: I
B: I and II Correct answer
C: II and III
D: I, II, and III
Correct Answer:
B. I and II
Explanation

The applicant, typically the owner or their designated representative (e.g., architect, engineer), is responsible for ensuring that all submitted documents demonstrate compliance with applicable codes and standards. This includes the primary construction documents, which must detail all required fire protection features (Statement I). It also includes specialized shop drawings for systems like fire sprinklers or alarms. While prepared by contractors, these drawings must be reviewed for accuracy and compliance by the applicant's design professional before submission to the Authority Having Jurisdiction (AHJ) (Statement II). The AHJ's plan review is a technical assessment of code compliance, not an audit of business arrangements; therefore, the status of construction contracts is outside its scope (Statement III).

Why Incorrect

A: This is incorrect because the applicant's responsibility extends beyond the initial construction documents to include the review and submission of compliant shop drawings. C: This is incorrect because the applicant is fundamentally responsible for the primary construction documents, and the status of contracts is not a matter for AHJ plan review. D: This is incorrect because ensuring contracts are in place is a project management or business function, not a technical requirement for the AHJ's plan review process.

References

1. NFPA Fire and Life Safety Inspection Manual, 9th Edition. Chapter 3, "The Plan Review Process," p. 48, states, "The applicant is responsible for submitting a complete set of construction documents..." and p. 50 clarifies the role of the design professional in reviewing shop drawings for conformity with the construction documents and code requirements before submission to the AHJ.

2. NFPA 1, Fire Code, 2021 Edition. Section 1.7.7.1 requires that "Construction documents shall be submitted...with each application for a permit," placing the responsibility on the applicant. Section 1.7.10.1 further requires that submittals, including shop drawings for fire protection systems, be provided to the AHJ for review, a process managed by the applicant's team.

3. Krasner, M. (2016). Building Department Administration, 4th Edition. International Code Council. Chapter 6, "The Permit Process," explains that the plan review function is to verify that documents "conform to the technical requirements of the code" and does not involve the verification of contractual agreements between the owner and builder.