CIMAPRA19-P03-1 practice question 12 of 35
M plc is an IT company that bids for large contracts to sell computer systems and also to service existing systems. M plc's senior management…
Choose your answer, then check it against the explanation.
M plc is an IT company that bids for large contracts to sell computer systems and also to
service existing systems. M plc's senior management has always set budgets which are hard to
achieve and have made no allowances for the recession.
The economy has improved and M plc's senior managers have made the budget even more
optimistic. The budgeted sales target has been increased by 40%.
In the past, sales staff have not tried to achieve the budget sales because it was generally believed
that the targets were impossible to reach.
M plc has recently appointed a new Sales Director who has decided that sales staff will
be dismissed if they fail to meet sales targets for three successive months. He is also looking
for higher sales margins than were achieved before.
What are the likely consequences of the new Sales Director's policy?
Question 12 of 35
Keep practicing
Take the free CIMAPRA19-P03-1 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CIMAPRA19-P03-1 practice questions
- Question 1JHU has recently completed an eight year project. The project was evaluated at a discount…
- Question 2A UK manufacturing company has simultaneously: • purchased a put option to sell USD 1mill…
- Question 3There are many method for appraising capital projects. Select ALL correct statements.
- Question 4Systems Development Lifecycle (SDLC) is used to manage risk within the development of new…
- Question 5James owns a small company which sometimes suffers from credit risk. Which of the followi…
- Question 6Company W produces mobile phone components and has recently tendered for a substantial co…