COBIT-DESIGN-AND-IMPLEMENTATION practice question 4 of 25
Which of the following tools would be MOST useful for measuring and monitoring performance and the realization of benefits from an EGIT implementation program plan project?
Full set: 120 questionsAn IT balanced scorecard (BSC) is a strategic performance management tool designed to translate strategy into a coherent set of performance measures. It goes beyond simple project tracking by measuring performance across multiple perspectives (e.g., financial, customer, internal process, learning and growth). This makes it the most suitable tool for monitoring the overall performance of an EGIT program and, crucially, for measuring the realization of strategic benefits and business value, which is the ultimate goal of the implementation.
B. Project management software tracks the execution of project tasks, schedules, and budgets but does not inherently measure the strategic benefits or business value realized.
C. A Gantt chart is a project scheduling tool that visualizes tasks over time. It is used for tracking project progress, not for measuring performance or benefits realization.
D. A RACI chart defines roles and responsibilities for project tasks. It is a governance tool for clarifying accountability, not a performance measurement tool.
1. ISACA, COBIT® 2019 Framework: Governance and Management Objectives, 2018, EDM01 Ensured Governance Framework Setting and Maintenance, p. 24. This objective includes metrics related to business value from I&T-enabled investments, a key component of a BSC.
2. ISACA, COBIT® 2019 Implementation Guide: Implementing and Optimizing an Information and Technology Governance Solution, 2018, Section 5.3 Phase 7: Review Effectiveness, p. 41. This phase focuses on monitoring success and value, for which a BSC is an ideal tool.
Keep practicing
Take the free COBIT-DESIGN-AND-IMPLEMENTATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other COBIT-DESIGN-AND-IMPLEMENTATION practice questions
- Question 1Who is responsible for performing a stakeholder satisfaction survey and gathering feedbac…
- Question 2Which of the following focus area variants should be considered when the role of IT desig…
- Question 3A CEO of a domestic enterprise plans to expand its operations globally. The CEO has selec…
- Question 5Which function within the IT corporate structure is responsible for classifying informati…
- Question 6During CSF life cycle action plan review, which of the following tasks is associated with…
- Question 7I&T-related issues, also called pain points: