CPIM-MPR practice question 24 of 25

Rough-cut capacity planning is best used to:

Full set: 105 questions
Answer options
A: assess the load on a work center.
B: evaluate the master production schedule. Correct answer
C: establish order priorities.
D: determine labor requirements.
Correct Answer:
B. evaluate the master production schedule.