CPIM-MPR practice question 19 of 25

Which of the following factors typically has the largest effect on the schedule developed by an advanced production scheduling (APS) system?

Full set: 105 questions
Answer options
A: Amount of past due work
B: Performance measures used
C: Precision of the capacity data
D: Priorities of the master schedule items Correct answer
Correct Answer:
D. Priorities of the master schedule items