CPIM-MPR practice question 22 of 25

Which of the following groups receives the LEAST benefit from extending the demand planning time fence in the master schedule?

Full set: 105 questions
Answer options
A: Manufacturing
B: Shipping
C: Customers Correct answer
D: Production scheduling
Correct Answer:
C. Customers