A company wants to minimize the cost of manufacture and also be flexible enough to adapt to changing needs. Changes to production schedules can result in the following EXCEPT:

Full set: 586 questions
Answer options
A: Cost increases due to rerouting, rescheduling, extra setups, expediting, and buildup of work-in- process inventory
B: Decreased customer service. A change in quantity of delivery can disrupt the schedule of other orders
C: Loss of credibility for the MPS and the planning process
D: Process create more scraps than needed than needed Correct answer
Correct Answer:
D. Process create more scraps than needed than needed