CPIM practice question 6 of 35

A priority plan for the components needed to make the products in the Master production schedule (MPS) is called:

Full set: 586 questions
Answer options
A: Production Activity control (PAC)
B: Material Requirements planning (MRP) Correct answer
C: Capacity Requirement planning
D: All of the above
Correct Answer:
B. Material Requirements planning (MRP)
Scroll to Top