CSM-001 practice question 25 of 25
You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information: Sprint 1: 10 pontos Sprint…
Choose your answer, then check it against the explanation.
You are the Scrum Master and your Development Team of 6 members has completed six Sprints with
the following information:
Sprint 1: 10 pontos
Sprint 2: 11 pontos
Sprint 3: 15 pontos
Sprint 4: 14 pontos
Sprint 5: 15 pontos
Sprint 6: 10 pontos
The remaining story points for product development total 42. What is the approximate number of
Sprint required to complete product development?
Question 25 of 25
Keep practicing
Take the free CSM-001 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CSM-001 practice questions
- Question 1What is the maximum amount of time a sprint retrospective should take?
- Question 2What is the primary objective of the daily scrum?
- Question 3Select which option best completes the following statement: _____________ is all about re…
- Question 4Who is required to attend the Daily Scrum?
- Question 5Agile software development also promotes industry best practices that _______________ and…
- Question 6Please select which statement is the most accurate: