CSSLP practice question 5 of 35
A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this?
Full set: 357 questionsRisk transference is a strategy that involves shifting the negative impact of a threat, along with ownership of the response, to a third party. In this scenario, the project manager is hiring an external company to handle the hardware work. By doing so, the financial and operational risks associated with that specific part of the project (e.g., delays, defects, cost overruns) are transferred to the vendor via a contractual agreement. The project itself does not eliminate the risk but reassigns the responsibility for managing it and bearing its consequences.
A. Exploit: This is a response strategy for positive risks (opportunities), where actions are taken to ensure the opportunity is realized, not for managing a potential threat.
B. Mitigation: Mitigation involves taking active steps to reduce the probability or impact of a risk, such as implementing quality controls, not shifting the entire responsibility to another party.
D. Avoidance: Risk avoidance would mean changing the project plan to eliminate the hardware work altogether, thereby removing the risk entirely, which is not what is happening here.
1. NIST Special Publication 800-30 Revision 1, Guide for Conducting Risk Assessments. (September 2012).
Section 2.4, RISK RESPONSE, Page 21: This section defines the four primary risk response options. It defines risk sharing (transference) as: "Shifting the burden of loss or impact of a risk to another party through legislation, contract, insurance, or other means." The scenario of hiring a company via contract is a direct example of this definition.
2. Purdue University, ITaP Risk Management Methodology. (2018).
Section 4.2, Risk Treatment, Page 7: This document outlines risk treatment options, stating, "Risk Transfer: Sharing the risk with another party who is better able to manage the risk. Examples include outsourcing an activity or purchasing insurance." This directly supports the answer.
3. Boehm, B. W. (1991). Software Risk Management: Principles and Practices. IEEE Software, 8(1), 32-41.
Section: Risk Management Techniques, Page 35: While discussing risk mitigation, the paper describes risk transfer as a key technique: "The main way to transfer risks is to subcontract the risky component to a vendor with more experience in that area." This academic source validates outsourcing as a form of risk transference.
Keep practicing
Take the free CSSLP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CSSLP practice questions
- Question 1Fred is the project manager of the CPS project. He is working with his project team to pr…
- Question 2You work as a system engineer for BlueWell Inc. You want to verify that the build meets i…
- Question 3An asset with a value of $600,000 is subject to a successful malicious attack threat twic…
- Question 4John works as a professional Ethical Hacker. He has been assigned the project of testing …
- Question 6Information Security management is a process of defining the security controls in order t…
- Question 7Which of the following techniques is used when a system performs the penetration testing …