CSSLP practice question 1 of 35
Fred is the project manager of the CPS project. He is working with his project team to prioritize the identified risks within the CPS project. He and the team are prioritizing risks for further analysis or action by assessing and combining the risks probability of occurrence and impact. What process is Fred completing?
Full set: 357 questionsThe process described is Perform Qualitative Risk Analysis. This is a standard project management process where identified risks are prioritized for further action. The prioritization is achieved by assessing each risk's probability of occurrence and its potential impact on project objectives. The output of this process is a ranked or grouped list of risks, which allows the project team to focus its attention on the most critical threats and opportunities. Fred's team is explicitly "assessing and combining the risks probability of occurrence and impact" to prioritize them, which is the definition of this process.
A. Risk identification: This is the process of determining which risks might affect the project and documenting their characteristics. The scenario states risks have already been "identified."
B. Risk Breakdown Structure creation: This involves creating a hierarchical decomposition of potential sources of risk. It is a tool for organizing risks, not the process of prioritizing them.
D. Perform quantitative analysis: This process numerically analyzes the effect of high-priority risks on overall project objectives. It is more in-depth and typically follows qualitative analysis.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 11.3, "Perform Qualitative Risk Analysis," p. 419. The text defines this process as "prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics."
2. National Institute of Standards and Technology (NIST). (2012). Guide for Conducting Risk Assessments (NIST Special Publication 800-30, Revision 1). Section 2.3.2, "Risk Analysis," p. 17. This section describes the analysis of risk, which involves considering "the likelihood of occurrence for the identified threats" and "the impact of the threats."
3. Goertzel, K. M., & Paza, C. (2012). Security in the Software Lifecycle. In M. Khosrow-Pour (Ed.), Software Development Techniques for Constructive Information Systems Design (pp. 316-341). IGI Global. Chapter 16, p. 326. The text discusses risk analysis within the SDLC, stating, "The first step in risk analysis is to determine the probability of the risk occurring and the impact... This is known as qualitative risk analysis."
4. Boehm, B. (1991). Software Risk Management: Principles and Practices. IEEE Software, 8(1), 32-41. https://doi.org/10.1109/52.62940. On page 34, the article discusses risk assessment, which includes the steps of risk identification, risk analysis (determining probability and loss/impact), and risk prioritization. This foundational paper aligns directly with the process described in the question.
Keep practicing
Take the free CSSLP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CSSLP practice questions
- Question 2You work as a system engineer for BlueWell Inc. You want to verify that the build meets i…
- Question 3An asset with a value of $600,000 is subject to a successful malicious attack threat twic…
- Question 4John works as a professional Ethical Hacker. He has been assigned the project of testing …
- Question 5A part of a project deals with the hardware work. As a project manager, you have decided …
- Question 6Information Security management is a process of defining the security controls in order t…
- Question 7Which of the following techniques is used when a system performs the penetration testing …
