CTAL-TM practice question 29 of 30

Following identification of a number of costly system performance failures late in the development lifecycle, your organisation has introduced a more…

Full set: 228 questions
Following identification of a number of costly system performance failures late in the development lifecycle, your organisation has introduced a more rigorous review process for system design documents and source code to enhance phase containment. There will be subsequent checks to see if the improved review process detects/prevents these types of performance defects which are likely to have the highest impact on the technical behavior of the system. You have been tasked with evaluating the current defect management tool that will be used to support the reviews and dynamic testing, to ensure that the correct defect data attributes will be captured to enable these checks to be done. Which three of the following attributes would be MOST effective? a) Phase of introduction b) Severity c) Steps to reproduce the failure d) Resolution details e) Phase of detection SELECT ONE OPTION
Answer options
A: a, b and e. Correct answer
B: a, b and c.
C: b. c and d.
D: b, d and e.
Correct Answer:
A. a, b and e.
Explanation

The organization's goal is to evaluate the effectiveness of a new review process in achieving "phase containment" for high-impact performance defects. Phase containment is measured by comparing the phase a defect was introduced against the phase it was detected; therefore, "Phase of introduction" (a) and "Phase of detection" (e) are mandatory attributes. Additionally, to filter for defects that have the "highest impact on the technical behavior," the "Severity" (b) attribute must be captured. Together, these three attributes directly enable the required checks.

Why Incorrect

Option B: "Steps to reproduce" (c) is essential for debugging but does not provide metrics for measuring phase containment or defect impact.
Option C: "Resolution details" (d) and "Steps to reproduce" (c) are operational lifecycle attributes, not analytical metrics for evaluating phase containment.
Option D: "Resolution details" (d) tracks how a defect was fixed, which offers no data on phase containment or the defect's initial technical impact.

References

- ISTQB Certified Tester Advanced Level Syllabus - Test Manager, Section 4.2 (Defect Management Data and Metrics).

- Black, R. (2014). Advanced Software Testing - Vol. 2: Guide to the ISTQB Advanced Certification as an Advanced Test Manager. Rocky Nook. (Chapter on Defect Management and Phase Containment).

Scroll to Top