CTAL-TM practice question 28 of 30
You are the Test Manager for a software house (SoftTech), who provide a core banking product to retail banks around the world to enable their…
Full set: 228 questionsThe project involves integrating with poorly documented systems and must strictly comply with Financial Conduct Authority (FCA) regulatory banking standards. Inspections are the most formal type of review, characterized by strict rules, checklists, and entry/exit criteria. They are specifically designed to verify that documentation conforms to set standards and regulations. Given the high-risk, regulated nature of the banking sector and the need to ensure the new integration documentation meets FCA standards, conducting formal inspections is the best and most appropriate approach.
B: Management reviews are designed to assess project progress, resource allocation, and management procedures, not to verify technical documentation conformance to regulatory standards. C: Audits evaluate overall compliance of processes or products and are typically conducted by independent external personnel, whereas the Test Manager is tasked with reviewing the documentation itself. D: Informal reviews lack the necessary rigor, documentation, and structured verification required to ensure compliance with strict regulatory banking standards.
1. ISTQB Certified Tester Advanced Level Syllabus - Test Manager (v2012), Section 4.3 "Managing Reviews", pp. 54-56.
2. IEEE Standard for Software Reviews and Audits (IEEE Std 1028-2008), Section 7 "Inspections", pp. 25-30. https://doi.org/10.1109/IEEESTD.2008.4601584
Keep practicing
Take the free CTAL-TM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CTAL-TM practice questions
- Question 1Which of the following is an advantage of specifying test conditions at a detailed level?…
- Question 2While mining the defect database for patterns of problems in the last release, a Test Man…
- Question 3You have been seeing a high number of rejections of defect reports The developers are com…
- Question 4In an Agile project, when Is it acceptable lo not write a formal defect report when a def…
- Question 5One of your team members is struggling to identify the requirements to be tested for a pr…
- Question 7What test process is included as part of TPI Next? [1]