CTAL-TM practice question 27 of 30

You have been asked to estimate the testing effort for an upgrade to a legacy product Your team did the testing on the last upgrade, and you have ascertained that this upgrade is about 10% bigger than the last one Given this information which estimation technique should you use to come up with the test effort number?

Full set: 228 questions
Answer options
A: Function points
B: Extrapolation Correct answer
C: Planning poker
D: Three-point estimation
Correct Answer:
B. Extrapolation
Explanation

Extrapolation is a metrics-based estimation technique where historical data from past projects is used to estimate the effort for a new, similar project. Since the team has exact historical data from the previous upgrade and knows the new upgrade is exactly 10% larger, they can extrapolate the previous effort by simply adding 10%. This is the most accurate and efficient method given the availability of highly relevant, recent historical metrics from the exact same team and product.

Why Incorrect

A. Function points require detailed functional requirements to calculate, which is unnecessary and time-consuming when direct historical effort data for a similar upgrade is already available.
C. Planning poker is an expert-based, consensus-driven technique typically used in Agile environments, not a metrics-based scaling approach based on historical percentages.
D. Three-point estimation requires calculating optimistic, pessimistic, and most likely estimates, rather than applying a direct 10% extrapolation from known past data.

References

1. ISTQB Certified Tester Advanced Level Syllabus - Test Manager (v2012), Section 3.2.3 "Test Estimation" (discusses metrics-based estimation and extrapolation).

2. Black, R. (2014). Advanced Software Testing - Vol. 2, 2nd Edition: Guide to the ISTQB Advanced Certification as an Advanced Test Manager. Rocky Nook. (Chapter 3: Test Planning, Monitoring and Control).