CTAL-TM practice question 26 of 30

When Is the metric for the percentage of requirements coverage defined?

Full set: 228 questions
Answer options
A: Test planning Correct answer
B: Test monitoring
C: Test execution
D: Test completion
Correct Answer:
A. Test planning
Explanation

According to the ISTQB Advanced Level Test Manager syllabus, the definition of metrics, including requirements coverage, is established during the test planning phase. Test planning involves defining the test objectives, exit criteria, and the specific metrics that will be used to monitor and control the testing process and evaluate completion. Defining these metrics upfront ensures that the test team knows exactly what data to collect during execution to accurately report on coverage and quality to stakeholders.

Why Incorrect

B. Test monitoring uses the predefined metrics to track progress and control the project, but it does not define them.
C. Test execution generates the raw data that feeds into the metrics, but the metrics themselves must be defined prior to this phase.
D. Test completion involves reporting on the final metrics to stakeholders, long after the metrics were initially defined and collected.

References

1. ISTQB Certified Tester Advanced Level Syllabus - Test Manager, Section 1.3 "Test Planning", detailing the definition of metrics and exit criteria.

2. International Software Testing Qualifications Board (ISTQB), "Advanced Level Syllabus: Test Manager," v3.0, Section 1.3.2.