CTAL-TM practice question 8 of 30
You are working with a development team who have a CI/CD pipeline implemented. They want to integrate your team's existing test automation into the…
Full set: 228 questionsThe scenario explicitly states that integrating the existing test automation into the CI/CD pipeline is technically possible but requires specific modifications to the test automation framework to handle results reporting. Because the tool has already been evaluated and deemed capable, the immediate requirement is equipping the team with the necessary skills to implement these technical changes. Providing targeted training ensures the team understands how to correctly modify the framework's architecture to successfully integrate with the CI/CD pipeline's reporting mechanisms, bridging the gap between the tool's capability and the team's current technical execution.
A: Incorrect because the scenario explicitly states the team has "already determined that this is technically possible," meaning fitness for purpose is already established. C: Incorrect because the decision to use the current tool has already been made; revisiting tool selection would unnecessarily delay the implementation phase. D: Incorrect because the prompt focuses on a technical implementation hurdle (framework modifications), not a financial, administrative, or licensing constraint.
1. ISTQB Certified Tester Advanced Level - Test Manager (CTAL-TM) Syllabus, Section 6.2: Test Tool Selection and Implementation.
2. ISTQB Certified Tester Advanced Level - Test Automation Engineer (CTAL-TAE) Syllabus, Section 3.2: Test Automation Architecture.
3. Humble, J., & Farley, D. (2010). Continuous Delivery: Reliable Software Releases through Build, Test, and Deployment Automation. Addison-Wesley Professional.
Keep practicing
Take the free CTAL-TM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CTAL-TM practice questions
- Question 1Which of the following is an advantage of specifying test conditions at a detailed level?…
- Question 2While mining the defect database for patterns of problems in the last release, a Test Man…
- Question 3You have been seeing a high number of rejections of defect reports The developers are com…
- Question 4In an Agile project, when Is it acceptable lo not write a formal defect report when a def…
- Question 5One of your team members is struggling to identify the requirements to be tested for a pr…
- Question 7What test process is included as part of TPI Next? [1]