CTFL4 practice question 12 of 25

Which of the following about typical information found within a test plan is FALSE?

Full set: 148 questions
Answer options
A: The need to temporarily have additional test personnel available for specific test phases and/or test activities
B: The conditions that must be met in order for the test execution activities to be considered completed.
C: The list of the product risks which have not been fully mitigated at the end of test execution. Correct answer
D: The conditions that must be met for part of all the planned activities to be suspended and resumed.
Correct Answer:
C. The list of the product risks which have not been fully mitigated at the end of test execution.
Explanation

A typical test plan includes various elements, such as resource requirements, test completion criteria, and suspension/resumption criteria. However, the list of product risks that have not been fully mitigated is generally not included in the test plan but rather in the risk management documentation. The test plan focuses on planning and executing tests, including resource allocation and defining criteria for test suspension and resumption. While risk management is crucial, unmitigated risks are typically documented in risk logs or separate risk management plans.
Reference: ISTQB CTFL Syllabus V4.0, Chapter 5.1.1, Test Planning  .