CTIL-001 practice question 5 of 10

Which of the following activities should be carried out at the start of this process?

Full set: 25 questions
Answer options
A: Marketing of the service to as many people as possible to reduce the risk of poor revenues.
B: Holding a workshop with as many stakeholders as possible to gain their views on the risks to the product and project. Correct answer
C: Meeting with the project manager to agree a bigger budget.
D: Meeting with the development manager to agree defect fix turn-around times.
Correct Answer:
B. Holding a workshop with as many stakeholders as possible to gain their views on the risks to the product and project.