Which of the following provides the best example of a product risk leading to a project risk?

Full set: 25 questions
Answer options
A: The signalling systems may have more defects than anticipated, leading to the need for more retesting to be carried out. Correct answer
B: There may be unexpected lags on the network traffic communication, causing drivers to slow the trains down unnecessarily.
C: The new development staff may require training for this type of system, which, if not carried out, may lead to an increase in the number of defects introduced.
D: The budget may need to be increased significantly during the project, otherwise there may be delays in the delivery of the system.
Correct Answer:
A. The signalling systems may have more defects than anticipated, leading to the need for more retesting to be carried out.