CWBSP practice question 1 of 35
An 8 in. (200 mm) Schedule 40 steel main is to be supported from a trapeze hanger. The trapeze hanger is to span between two joists which are 7.5 ft…
Choose your answer, then check it against the explanation.
An 8 in. (200 mm) Schedule 40 steel main is to be supported from a trapeze hanger. The trapeze
hanger is to span between two joists which are 7.5 ft (2.3 m) apart. What is the minimum size of
steel pipe the trapeze member is to be made of?
Question 1 of 35
Keep practicing
Take the free CWBSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CWBSP practice questions
- Question 2What is the minimum calculated design area for a dry system protecting a light hazard att…
- Question 3A paddle-type water flow alarm indicator shall be installed only in
- Question 4What standard applies for underground malleable iron threaded fittings of Class 150?
- Question 5In areas using HVLS fans, where must the fans be located in regards to sprinkler placemen…
- Question 6What piping material is acceptable for the suction and discharge piping pressure maintena…
- Question 7A 4.2 K-factor sprinkler must deliver 17 gpm (692 mm/min). What pressure is required?