DEVELOPMENT-LIFECYCLE-AND-DEPLOYMENT-ARCHITECT practice question 28 of 30

Universal Containers is building a new complex integration to a legacy system. the legacy system is also going through a major upgrade. Senior leadership has committed to the board that the combined programs will be completed on time. What is the risk with this plan?

Full set: 227 questions
Answer options
A: The deadline is scheduled during a Salesforce release
B: The project team has decided to use the Waterfall methodology
C: The legacy system team is using an Agile methodology
D: Multiple work -streams with dependencies could impact the go-live Correct answer
Correct Answer:
D. Multiple work -streams with dependencies could impact the go-live
Explanation

The primary risk is the high degree of interdependency between the two major, concurrent projects. The Salesforce integration's success is contingent on the legacy system's upgrade, and vice versa. A delay, scope change, or technical issue in one workstream will directly and negatively impact the other. This "coupled" dependency creates a significant risk of timeline slippage for the entire program, making the committed deadline difficult to achieve. Managing cross-team dependencies is a critical risk factor in any large-scale program, regardless of the methodologies used by the individual teams.

Why Incorrect

A. A Salesforce release is a manageable, predictable event. While it requires planning, it is not the primary risk compared to a major system dependency.
B. The choice of methodology (Waterfall) is a process detail; the core risk stems from the technical and timeline dependencies between the two systems, not the process itself.
C. Mismatched methodologies can create friction, but this is a process challenge, not the fundamental risk of one project's failure causing the other's failure.

References

1. Salesforce Well-Architected, (2023). Reliable. "Manage Dependencies". This framework explicitly calls out that "Dependencies on external systems... can introduce risk." It recommends identifying and planning for these dependencies to ensure system reliability and project success.

2. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition. "Section 2.7: Navigating Complexity". This guide identifies systemic complexity, including the number and diversity of system components and dependencies, as a key factor influencing project outcomes.

3. Salesforce Architects, (2022). The Architect's Guide to Development Lifecycle and Deployment. "Chapter 2: Understand the Development Lifecycle". This guide discusses assessing project complexity, where integrations and dependencies on external systems are key contributors to risk.