DEVELOPMENT-LIFECYCLE-AND-DEPLOYMENT-ARCHITECT practice question 29 of 30
What is the responsibility of the Technical Architect within a Change Control Board meeting?
Full set: 227 questionsA Change Control Board (CCB) is a governance body responsible for making "go/no-go" decisions on releases. The Technical Architect is the senior technical authority on the project or within the organization. Their specific responsibility within a CCB meeting is to provide the final technical assessment and approval, confirming that the release is architecturally sound, technically feasible, stable, and ready for deployment into the production environment from a technical standpoint. This approval is a critical gate in the release management process.
A. Prioritizing the product roadmap is a strategic activity typically owned by a Product Manager or steering committee, not the TA's role within a tactical CCB meeting.
B. Code reviews are a development-phase activity that should be completed before the release candidate is presented to the CCB for approval.
C. Troubleshooting past deployment errors is a reactive, operational task. While its findings may inform CCB decisions, it is not the TA's primary function during the meeting.
1. Salesforce. (2019). Salesforce Center of Excellence. Whitepaper. This document outlines governance structures, where the CCB is a key component. It implicitly defines the roles of participants, with the architect as the guardian of technical integrity and standards, leading to their approval role.
2. Salesforce Trailhead. (n.d.). Application Lifecycle and Development Models. Module: "Release Management". This module describes the release process, including the final approval steps before deployment, which is the function of a CCB where a technical lead or architect would have a key voice.
3. Project Management Institute (PMI). (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 4.6 "Perform Integrated Change Control". This standard describes the role of a CCB in reviewing and approving change requests, a process for which the technical expert (i.e., architect) provides critical input and approval.
Keep practicing
Take the free DEVELOPMENT-LIFECYCLE-AND-DEPLOYMENT-ARCHITECT practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other DEVELOPMENT-LIFECYCLE-AND-DEPLOYMENT-ARCHITECT practice questions
- Question 1Universal Containers (UC) has multiple development teams that work on separate streams of…
- Question 2In architect is working on a project that relies on functionality that cannot be deployed…
- Question 3Universal Containers (UC) wants to shorten their deployment time to production by control…
- Question 4What is the process used to initiate a connection for change sets?
- Question 5Universal Containers is looking to construct a continuous integration process to help man…
- Question 6Universal Containers has three types of releases in their release management strategy: da…