H13-629 practice question 25 of 35

Information of the disaster recovery research Beijing project mainly includes three aspects (Who / What / Why) description. Which of the following is true? (Multiple choice.)

Full set: 364 questions
Answer options
A: A bank has more than XX customers and XX corporate customers.
B: Loss of data will result in substantial loss of business interruption and may also result in significant financial loss.
C: Business interruption has a huge impact, and the interruption time of business deployment <2h. Correct answer
D: Customers want to build two live-action data centers in the same city and realize double-live of the key business systems. The disaster recovery plan RPO = 0, RTO = 0 Correct answer
Correct Answer:
C. Business interruption has a huge impact, and the interruption time of business deployment; D. Customers want to build two live-action data centers in the same city and realize double-live of the key business systems. The disaster recovery plan RPO = 0, RTO = 0
Scroll to Top