H19-321 practice question 28 of 35

For Huawei's network evaluation and optimization service process, which of the following is the correct service process?

Full set: 265 questions
Answer options
A: Live network data collection--- live network configuration restoration--- target network design --- implementation plan development--- optimization operation implementation --- acceptance test Correct answer
B: Target network design --- live network data collection --- live network configuration restore--- implementation plan development--- optimization operation implementation --- acceptance test
C: The design of the target network network --- the data collection --- the live network is --- the development of the implementation scheme --- the implementation of the live network configuration restoration --- the optimization of the operation Acceptance testing try
D: Live network data collection--- live network configuration and restoration --- implementation plan development--- target network design --- optimized operation implementation Acceptance testing try
Correct Answer:
A. Live network data collection--- live network configuration restoration--- target network design --- implementation plan development--- optimization operation implementation --- acceptance test
Explanation

The correct sequence for a network evaluation and optimization project follows a logical progression. It begins with understanding the current state by collecting data and restoring the live network configuration for analysis. Based on this baseline, a target network is designed. An implementation plan is then developed to bridge the gap between the current and target states. Finally, the optimization is executed, and an acceptance test is performed to verify that the objectives have been met.

Why Incorrect

B. This option incorrectly places target network design before data collection, which is illogical as design requires baseline data.
C. This option has an illogical flow, placing implementation before configuration restoration and contains unclear phrasing.
D. This option incorrectly places target network design after the development of the implementation plan, which is out of sequence.

References

1. Huawei Enterprise Support, "Network Planning and Optimization Service Description". The document outlines the service workflow which generally follows the sequence of Assessment (including data collection), Planning and Design, Implementation, and Verification. This aligns with the logical flow presented in option A. (Specific document ID: Can vary, but the process is standard in Huawei's service descriptions for NPO).

2. Huawei Learning, "HCIP-Datacom-Network Automation Developer V1.0 Course Material". Module on Network O&M and Automation discusses the lifecycle of network management, which starts with data collection and analysis before any design or implementation changes are planned. (Section: Network O&M Lifecycle).