H19-321 practice question 15 of 35
The smaller the PUE value, the higher the degree of greening of a data center.
Full set: 265 questionsPower Usage Effectiveness (PUE) is the standard industry metric for measuring the energy efficiency of a data center. It is calculated by dividing the total power entering the data center by the power used by the IT equipment. A PUE of 1.0 represents a perfectly efficient data center where 100% of the power is used by IT equipment. Any value greater than 1.0 indicates power is being used for overhead like cooling and lighting. Therefore, a lower PUE value signifies less wasted energy and a more efficient, or "greener," data center.
B. This is factually incorrect. A higher PUE value indicates lower efficiency and more energy waste, which is the opposite of being "green."
1. The Green Grid. (2012). PUE: A Comprehensive Examination of the Metric. White Paper #49. Section 2, "PUE and its Derivatives," defines the metric and its interpretation, stating that lower values are better.
2. Huawei Technologies Co., Ltd. (2021). Green Data Center: The Fast Track to a Sustainable Digital World. White Paper. Page 5, "Innovating for xPUE," discusses the importance of lowering PUE as a key goal for achieving green, low-carbon data centers.
3. Gao, P. (2016). A review of data center cooling technologies, trends and metrics. Advances in Mechanical Engineering, 8(10). https://doi.org/10.1177/1687814016668660. This academic paper discusses PUE as the "most popular metric" for energy efficiency, where a lower value is desirable.
Keep practicing
Take the free H19-321 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other H19-321 practice questions
- Question 1Huawei's special maintenance support services include?
- Question 2Huawei Data Center L1 Integration Service quotation includes (multiple choice)
- Question 3What methods does UniSTAR SCT Configurator support for maintenance service quotation? (Mu…
- Question 4What is not the key point of data center L1 total integration service expansion?
- Question 5For non-distributed products, which of the following customer support service products is…
- Question 6Typical application scenarios for SmArtMigrAtion to achieve data migration are ( (multipl…