ICGB practice question 15 of 30

A Belt concludes a Lean Six Sigma project with the creation of a Control Plan. At what point can the Control Plan be closed?

Full set: 200 questions
Answer options
A: Never, a Control Plan is a living document Correct answer
B: As soon as the Champion signs off
C: Within 30 days of the LSS project review team meeting
D: After the project has been presented at the recognition event
Correct Answer:
A. Never, a Control Plan is a living document
Explanation

A Control Plan is a core component of the Quality Management System and is considered a "living document." It is created during the Control phase of a DMAIC project to ensure the gains are sustained. However, its life extends far beyond the project's closure. The process owner is responsible for maintaining and updating the Control Plan whenever the process, measurement systems, or customer requirements change. It is never "closed" or finalized; it evolves with the process it is designed to control.

Why Incorrect

B. The Champion's sign-off typically closes the Lean Six Sigma project, not the Control Plan. The sign-off signifies the handover of the solution to the process owner.
C. This suggests an arbitrary deadline. The Control Plan's lifecycle is tied to the process it controls, not to a project meeting schedule.
D. A recognition event is for celebrating project success and has no procedural impact on the status of operational quality documents like the Control Plan.

References

1. Purdue University. (n.d.). Lean Six Sigma - Control Phase. Retrieved from https://www.purdue.edu/leansixsigma/controlphase.html. The description of the Control Plan emphasizes its role in ongoing monitoring: "The purpose of the Control Plan is to ensure that the gains from the project are sustained over time." This implies a continuous, not a finite, existence.

2. University of Michigan. (n.d.). Six Sigma: Control Phase. Retrieved from https://www.micquality.com/sixsigma/controlphase.htm. The materials describe the Control Plan as a document that "describes the system for controlling the process" and is handed over to the process owner, indicating its ongoing operational function beyond the project's life.