ICGB practice question 8 of 30

The reported Cpk for a process with an average of 94 units, a spread of 22 units and upper and lower specification limits of 125 and 80 units would be?

Full set: 200 questions
Answer options
A: 0.64
B: 1.27 Correct answer
C: 1.84
D: 2.12
Correct Answer:
B. 1.27
Explanation

The Process Capability Index (Cpk) measures how close a process is to its specification limits, relative to the process spread. It is calculated as the minimum of Cpu and Cpl. First, the standard deviation (σ) is estimated from the spread (Spread = 6σ), so σ = 22/6 ≈ 3.67. Then, 3σ = 11. Cpu = (USL - Average) / 3σ = (125 - 94) / 11 = 31 / 11 ≈ 2.82. Cpl = (Average - LSL) / 3σ = (94 - 80) / 11 = 14 / 11 ≈ 1.27. Cpk is the lesser of these two values, which is 1.27.

Why Incorrect

A. 0.64: This value is incorrect and does not result from the standard Cpk calculation with the given inputs.
C. 1.84: This value is incorrect. It might be a miscalculation of either Cpl or Cpu, or an average of the two, which is not the Cpk formula.
D. 2.12: This value is incorrect. It is not the minimum of Cpu and Cpl and does not align with the Cpk calculation.

References

1. Montgomery, D. C. (2013). Introduction to Statistical Quality Control (7th ed.). Wiley. Chapter 8, "Process Capability Analysis," Section 8-2.3, pp. 372-374. The formulas for Cpl, Cpu, and Cpk are defined and explained.

2. NIST/SEMATECH. (n.d.). e-Handbook of Statistical Methods. Section 6.3.2.1, "Process Capability Indices." The handbook provides the standard formulas Cpk = min[(USL-μ)/3σ, (μ-LSL)/3σ]. Retrieved from https://www.itl.nist.gov/div898/handbook/pmc/section3/pmc321.htm

3. Purdue University. (n.d.). IE 53000 - Quality Control Course Notes. Module: Process Capability. The courseware details the calculation of Cpk, emphasizing it is the minimum of the upper and lower capability indices.