Training cost $6,500 and a project required an initial investment of $47,500. If the project yields monthly savings of $3,500 beginning after 4 months, what is the payback period in months, before money costs and taxes?

Full set: 200 questions
Answer options
A: 9.7
B: 15.4
C: 19.4 Correct answer
D: 23.7
Correct Answer:
C. 19.4
Explanation

The payback period is the time required for the cumulative savings from a project to equal the total initial investment.
1. Calculate the total initial investment: Training Cost + Project Investment = $6,500 + $47,500 = $54,000.
2. Calculate the time required to recover the investment from the point savings begin: $54,000 / $3,500 per month = 15.43 months.
3. Add the initial delay period before savings start: 4 months (delay) + 15.43 months (recovery) = 19.43 months. The total payback period is approximately 19.4 months.

Why Incorrect

A. This value is incorrect; it likely results from a miscalculation of the total investment or a failure to account for the delay period.
B. This value (15.4) represents only the time to recoup the investment, incorrectly ignoring the initial 4-month delay before savings begin.
D. This value is incorrect and does not correspond to the correct calculation based on the provided numbers.

References

1. Park, C. S. (2019). Contemporary Engineering Economics (7th ed.). Pearson. Chapter 9, "Benefit-Cost Analysis," defines the payback period as the time it takes for a project's cumulative cash flow to equal its initial investment. The calculation method is Investment / Annual (or periodic) Savings.

2. Thuesen, G. J., & Fabrycky, W. J. (2001). Engineering Economy (9th ed.). Prentice Hall. Chapter 5, "Evaluating a Single Project," describes the payback period calculation as Initial Cost / Uniform Annual Benefit, which is the principle applied here on a monthly basis.

3. MIT OpenCourseWare. (2004). 15.010 / 15.011 Economic Analysis for Business Decisions, Fall 2004. Lecture Notes, "Investment Decisions: The Certainty Case." The notes define the payback period and provide the formula: Payback Period = Initial Investment / Annual Cash Flow. The question's scenario simply adds a delay period to this fundamental calculation.