IDPX practice question 14 of 25
Which space would MOST likely have a dedicated HVAC system?
Full set: 175 questionsA computer room houses sensitive electronic equipment that generates a significant and constant sensible heat load. It requires year-round cooling, precise temperature and humidity control, and often operates 24/7, independently of the main building's occupancy schedule. These unique and critical environmental requirements are fundamentally different from those of general office or public spaces, necessitating a dedicated, independent HVAC system to ensure equipment reliability and prevent overheating. This contrasts with spaces designed primarily for human comfort, which can be served by zoned central systems.
A. An office in a high rise is typically served by the building's central HVAC system as part of a larger zone, not requiring a dedicated unit.
C. A healthcare lobby's HVAC needs, while important for comfort and air quality, are generally met by a zone within the main building's system.
1. Grondzik
W. T.
& Kwok
A. G. (2019). Mechanical and Electrical Equipment for Buildings (13th ed.). Wiley. In Chapter 13
"HVAC Systems: Analysis and Selection
" the text discusses the need for special HVAC considerations for spaces with high internal heat gains
such as computer rooms
often requiring separate
dedicated systems to handle the unique load profile (pp. 518-519).
2. American Society of Heating
Refrigerating and Air-Conditioning Engineers (ASHRAE). (2019). ASHRAE Handbook—HVAC Applications. Chapter 21
"Data Centers and Telecommunication Facilities." Section 21.1 states
"The need for close control of temperature and humidity
high sensible heat ratios
and high air change rates in data centers requires dedicated air-conditioning systems."
3. Mehta
M. P.
Scarborough
W.
& Armpriest
D. (2018). Building Construction: Principles
Materials
and Systems (3rd ed.). Pearson. Chapter 20
"Heating
Ventilating
and Air-Conditioning (HVAC) Systems
" explains that spaces with unusual loads or operating schedules
such as computer rooms
are prime candidates for separate zoning or dedicated systems to operate efficiently and effectively (p. 865).
Keep practicing
Take the free IDPX practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other IDPX practice questions
- Question 1Prior to the contract document phase, a designer should meet with a client for what purpo…
- Question 2Contract documents serve as the legal contract between
- Question 3During which phase is it BEST to consider integrating a security system in a project?
- Question 4What floor finish would BEST support a passive solar design strategy in a hot arid climat…
- Question 5While performing a survey of an existing elevator lobby in a sprinklered commercial build…
- Question 6On a small project with an unclear scope involving multiple stakeholders, which fee metho…