IIA-CIA-PART3 practice question 32 of 35

An organization created a formalized plan for a large project. Which of the following should be the first step in the project management plan?

Full set: 516 questions
Answer options
A: Estimate time required to complete the whole project.
B: Determine the responses to expected project risks.
C: Break the project into manageable components. Correct answer
D: Identify resources needed to complete the project
Correct Answer:
C. Break the project into manageable components.
Explanation

The first step in creating a detailed project management plan is to define the project's scope and break the work down into smaller, more manageable components. This process is known as creating a Work Breakdown Structure (WBS). The WBS is a foundational element of project planning because it defines all the work to be done. All other planning activities, such as estimating time, identifying resources, and planning risk responses, depend on having a clear understanding of the project's components as defined in the WBS.

Why Incorrect

A. Estimate time required to complete the whole project: Time estimation can only be done accurately after the specific work components (the WBS) have been identified.
B. Determine the responses to expected project risks: Risk identification and response planning are subsequent planning processes that rely on the defined scope, schedule, and budget.
D. Identify resources needed to complete the project: Resource identification is dependent on first knowing the specific tasks and components that need to be completed.

References

1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 5.4, "Create WBS," describes this as "the process of subdividing project deliverables and project work into smaller, more manageable components." It is a key process in the Project Scope Management knowledge area, which is foundational to all other planning.

2. Larson, E. W., & Gray, C. F. (2017). Project Management: The Managerial Process (7th ed.). McGraw-Hill Education. Chapter 4, "Defining the Project," emphasizes that creating the WBS is a primary step after the scope statement is developed.

3. MIT OpenCourseWare. (2012). 16.852J / ESD.352J Project Management. Fall 2012. Lecture 5, "Project Planning: WBS, OBS, and Costing," presents the WBS as the starting point for detailed planning.