IIA-CIA-PART3 practice question 32 of 35
An organization created a formalized plan for a large project. Which of the following should be the first step in the project management plan?
Full set: 516 questionsThe first step in creating a detailed project management plan is to define the project's scope and break the work down into smaller, more manageable components. This process is known as creating a Work Breakdown Structure (WBS). The WBS is a foundational element of project planning because it defines all the work to be done. All other planning activities, such as estimating time, identifying resources, and planning risk responses, depend on having a clear understanding of the project's components as defined in the WBS.
A. Estimate time required to complete the whole project: Time estimation can only be done accurately after the specific work components (the WBS) have been identified.
B. Determine the responses to expected project risks: Risk identification and response planning are subsequent planning processes that rely on the defined scope, schedule, and budget.
D. Identify resources needed to complete the project: Resource identification is dependent on first knowing the specific tasks and components that need to be completed.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 5.4, "Create WBS," describes this as "the process of subdividing project deliverables and project work into smaller, more manageable components." It is a key process in the Project Scope Management knowledge area, which is foundational to all other planning.
2. Larson, E. W., & Gray, C. F. (2017). Project Management: The Managerial Process (7th ed.). McGraw-Hill Education. Chapter 4, "Defining the Project," emphasizes that creating the WBS is a primary step after the scope statement is developed.
3. MIT OpenCourseWare. (2012). 16.852J / ESD.352J Project Management. Fall 2012. Lecture 5, "Project Planning: WBS, OBS, and Costing," presents the WBS as the starting point for detailed planning.
Keep practicing
Take the free IIA-CIA-PART3 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other IIA-CIA-PART3 practice questions
- Question 1A company records income from an investment in common stock when it does which of the fol…
- Question 2Which of the following statements is true regarding an organization's chief audit executi…
- Question 3A new manager received computations of the internal fate of return regarding the project …
- Question 4An internal auditor was asked to review an equal equity partnership. In one sampled trans…
- Question 5A small chain of grocery stores made a reporting error and understated its ending invento…
- Question 6An internal audit engagement team found that the risk register of the project under revie…
