IIA-CRMA practice question 34 of 35

Which of the following are components of the COSO enterprise risk management framework? 1. Objective setting. 2. External environment. 3. Data collection. 4. Control activities.

Full set: 283 questions

Domain Risk Management Assurance

Answer options
A: 1 and 3 only
B: 1 and 4 only Correct answer
C: 2 and 3 only
D: 2 and 4 only
Correct Answer:
B. 1 and 4 only
Explanation

The Committee of Sponsoring Organizations of the Treadway Commission (COSO) "Enterprise Risk Management — Integrated Framework" (2004) explicitly identifies eight interrelated components. Among these are "Objective Setting" and "Control Activities." Objective setting is a precondition for event identification, risk assessment, and risk response. Control activities are the policies and procedures established and implemented to help ensure the risk responses are effectively carried out. The updated 2017 framework also includes "Strategy and Objective-Setting" as a core component and incorporates control activities within the "Performance" component.

Why Incorrect

External environment: This is a critical factor considered when setting strategy and objectives, but it is not a standalone component of the COSO ERM framework. Data collection: This is an essential activity that supports multiple components, such as risk assessment and monitoring, but it is not defined as a formal component itself.

References

1. Committee of Sponsoring Organizations of the Treadway Commission (COSO). (2004). Enterprise Risk Management — Integrated Framework: Executive Summary. Page 4. Retrieved from https://www.coso.org/Documents/COSO-ERM-Executive-Summary.pdf. The document lists the eight components, explicitly including "Objective Setting" and "Control Activities."

2. Committee of Sponsoring Organizations of the Treadway Commission (COSO). (2017). Enterprise Risk Management—Integrating with Strategy and Performance: Executive Summary. Page 6. Retrieved from https://www.coso.org/Documents/2017-COSO-ERM-Integrating-with-Strategy-and-Performance-Executive-Summary.pdf. This framework lists "Strategy and Objective-Setting" as the second component. Control activities are a key part of the "Performance" component, specifically under the principle of "Implements Risk Responses."

3. Moeller, R. R. (2011). COSO Enterprise Risk Management: Understanding the New Integrated ERM Framework. John Wiley & Sons. Chapter 3, "The COSO ERM Framework," details the eight components from the 2004 framework, providing in-depth descriptions of "Objective Setting" and "Control Activities."