INFORMATION-TECHNOLOGY-MANAGEMENT practice question 14 of 30

Which phase of the Rational Unified Process (RUP) assigns ownership of a system to stakeholders?

Full set: 210 questions
Answer options
A: Transition Correct answer
B: Inception
C: Elaboration
D: Construction
Correct Answer:
A. Transition
Explanation

The Transition phase of the Rational Unified Process (RUP) focuses on deploying the software product to the user community. The primary objective of this phase is to ensure that the system is ready for operation and is handed over to the end-users. Key activities include beta testing, user training, data conversion, and final deployment. This process culminates in the formal transfer of the system's ownership and maintenance responsibility from the development team to the stakeholders, such as the operations team and the end-user organization.

Why Incorrect

B. Inception: This initial phase focuses on establishing the business case, defining the project scope, and securing stakeholder agreement, not transferring system ownership.
C. Elaboration: This phase deals with analyzing requirements, defining a robust architecture, and planning the project; the system is not yet ready for handover.
D. Construction: This phase involves the development and testing of the software. The system is still being built and is not yet complete for deployment or ownership transfer.

References

1. Kruchten

P. (2003). The Rational Unified Process: An Introduction (3rd ed.). Addison-Wesley Professional. In Chapter 3

"Dynamic Structure: A Process Lifecycle

" the Transition phase is described with the objective: "to transition the software product to the user community" (p. 35). This includes activities that ensure users are self-sufficient.

2. Larman

C. (2004). Applying UML and Patterns: An Introduction to Object-Oriented Analysis and Design and Iterative Development (3rd ed.). Prentice Hall. Chapter 2

"Iterative

Evolutionary

and Agile

" describes the RUP phases

stating the Transition phase's purpose is to "put the system into production use" (p. 38).

3. Jacobson

I.

Booch

G.

& Rumbaugh

J. (1999). The Unified Software Development Process. Addison-Wesley. In Chapter 8

"The Process Lifecycle

" the Transition phase is detailed as the period when the product moves from the development organization to the end-user organization (p. 121).