ISO-BCMS-22301 practice question 19 of 35
Which of the following is about planning and arrangement of BCM tasks into a proper order of relationship to achieve the defined outcomes?
Full set: 100 questionsCoordination is the fundamental management function of integrating and synchronizing the activities, responsibilities, and resources of an organization to achieve specific, common objectives. In the context of a Business Continuity Management (BCM) system, coordination involves the deliberate planning and arrangement of various BCM tasks (e.g., incident response, communication, recovery) into a logical and effective sequence. This ensures that all elements of the business continuity plan work together harmoniously to meet the defined recovery time objectives (RTOs) and other continuity goals following a disruption.
A. Communication is the process of exchanging information, which is essential for effective coordination, but it is not the act of arranging or ordering the tasks themselves.
B. Analysis is the process of examining business impacts and risks (e.g., BIA, RA) to provide the foundational information needed for planning, not the arrangement of the response tasks.
D. Performance relates to the execution of tasks and the evaluation of their effectiveness (as in Clause 9 of ISO 22301), which is a result of good planning and coordination, not the act of arranging the plan.
1. ISO 22300:2021, Security and resilience — Vocabulary, Clause 3.45, defines coordination as the "integration of the activities of separate entities to accomplish a common objective." This definition directly aligns with the question's description of arranging tasks in a proper order to achieve defined outcomes.
2. ISO 22301:2019, Security and resilience — Business continuity management systems — Requirements, Clause 8.4.2, requires the establishment of a response structure to ensure an effective response. This structure's effectiveness is entirely dependent on the coordination of teams, tasks, and resources as described in the question.
3. Wong, W. C. (2009). A framework for implementing business continuity management. In IT Governance, Risk and Compliance Management. This academic text discusses BCM implementation, where coordination is presented as a critical success factor for integrating various BCM components, from risk assessment to recovery execution, to achieve the organization's continuity objectives. The concept of arranging tasks in a proper relationship is central to this integration. (Note: This is a conceptual reference to the role of coordination in BCM frameworks discussed in academic literature).
Keep practicing
Take the free ISO-BCMS-22301 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other ISO-BCMS-22301 practice questions
- Question 1Non-compliance can often lead to undesirable outcomes.
- Question 2Which one of the following initiative of Business Continuity Management is a regulatory s…
- Question 3Which step in PDCA Cycle maintains communication with key stakeholders?
- Question 4The PDCA paradigm cycle is widely recognized as a process-centric approact?
- Question 5____________________ manages the full spectrum of risks and their combined impact as an i…
- Question 6______________ are individuals or groups that have an interest in the organization's perf…