ISTQB-ATM practice question 13 of 15
In the next two months some new features will be constantly added to new releases of a project you are working on as Test Manager. You have…
Choose your answer, then check it against the explanation.
In the next two months some new features will be constantly added to new releases of a project you
are working on as Test Manager.
You have identified as one of the main project risks, that the requirements specification will still be
incomplete when your team starts the test design and implementation phase.
Some requirements will most likely be completed too late to allow a proper test preparation. You and
your test team have already worked on several similar past projects in the same organization.
Which one of the following options would you expect to be the most effective at mitigating this risk?
K4 3 credits
Question 13 of 15
Keep practicing
Take the free ISTQB-ATM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other ISTQB-ATM practice questions
- Question 2You are the Test Manager on a project following an iterative life-cycle model. The projec…
- Question 3The following are the exit criteria described in the test plan of a software product: EX1…
- Question 4You are the Test Manager of a new project aimed at developing a software system that must…
- Question 5The main objectives the senior management team wants to achieve are: - to reduce the cost…
- Question 7During the system testing phase a tester from your test team observes a failure in the sy…
- Question 8Consider the following statements describing the importance of improving the test process…