ISTQB-ATM practice question 4 of 15
You are the Test Manager of a new project aimed at developing a software system that must be certified at level B of the DO-178B standard. The…
Choose your answer, then check it against the explanation.
You are the Test Manager of a new project aimed at developing a software system that must be
certified at level B of the DO-178B standard. The project will follow a V-Model software development
life cycle and it will have four formal levels of testing: component, integration, system and
acceptance testing.
You must produce the test plan documentation for this project by providing an adequate
coordination across the four levels of testing in order to assure audit ability.
Which of the following answers would you expect to best describe how to organize the test plan?
K3 2 credits
Question 4 of 15
Keep practicing
Take the free ISTQB-ATM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other ISTQB-ATM practice questions
- Question 2You are the Test Manager on a project following an iterative life-cycle model. The projec…
- Question 3The following are the exit criteria described in the test plan of a software product: EX1…
- Question 5The main objectives the senior management team wants to achieve are: - to reduce the cost…
- Question 7During the system testing phase a tester from your test team observes a failure in the sy…
- Question 8Consider the following statements describing the importance of improving the test process…
- Question 9You are working on a project to develop an authentication system for an e-commerce websit…