ISTQB-ATM practice question 9 of 15
You are working on a project to develop an authentication system for an e-commerce website. This system provides two features: Registration and…
Full set: 64 questionsThe question requires identifying the option that is NOT a product risk. Product risks, also known as quality risks, are potential failures of the software to meet specified requirements or user expectations. Options B, C, and D all describe functional defects or security vulnerabilities where the system behaves incorrectly, thus representing clear product risks.
Option A describes the late delivery of a feature, which impacts the project timeline and the ability to conduct testing as planned. This is a classic example of a project risk, which pertains to the management and execution of the project (e.g., schedule, budget, resources), rather than a defect in the product itself.
B. This is a product risk because the system fails to meet a specific functional requirement—displaying a special warning for a special user.
C. This is a critical product risk as it describes a severe security vulnerability and a failure of the core authentication functionality.
D. This is also a critical product risk, representing a major security flaw and a failure of the system's primary authentication logic.
1. ISTQB Advanced Level Syllabus, Test Manager, Version 2012: Section 2.3.1, "Introduction to Risk Management," page 14, distinguishes between the two risk types. It defines project risks as those surrounding the project's ability to deliver its objectives, citing "supplier issues" (such as late delivery) as an example. It defines product risks as the possibility that the system might fail to satisfy user expectations, such as "software that does not perform its intended functions."
2. ISTQB Glossary of Testing Terms, Version 4.2:
Product Risk: Defined as "A risk directly related to the test object," which is "the possibility that a work product...may fail to satisfy the legitimate needs of its users and/or stakeholders." Options B, C, and D fall under this definition.
Project Risk: Defined as "A risk related to the management and control of a (test) project," with examples including "lack of staffing, strict deadlines, changing requirements." The scenario in option A, a delay impacting the test schedule, is a project risk.
Keep practicing
Take the free ISTQB-ATM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other ISTQB-ATM practice questions
- Question 2You are the Test Manager on a project following an iterative life-cycle model. The projec…
- Question 3The following are the exit criteria described in the test plan of a software product: EX1…
- Question 4You are the Test Manager of a new project aimed at developing a software system that must…
- Question 5The main objectives the senior management team wants to achieve are: - to reduce the cost…
- Question 7During the system testing phase a tester from your test team observes a failure in the sy…
- Question 8Consider the following statements describing the importance of improving the test process…