L4M3 practice question 13 of 25
In order to monitor supplier’s performance, an organization decides to draft performance management frameworks. Which of the following are the components of a performance management framework? Select THREE that apply:
Full set: 258 questionsA robust supplier performance management framework is built on three core components. First, Key Performance Indicators (KPIs) are selected to quantify and measure the critical aspects of performance. Second, specific, measurable, achievable, relevant, and time-bound Targets are established for each KPI, defining the expected level of performance. Third, the framework must outline the Consequences of meeting, exceeding, or failing to meet these targets. These consequences can include incentives and rewards for good performance or remedies and penalties for poor performance, creating a clear link between supplier actions and outcomes.
D. Indemnity: This is a legal clause within a contract that provides financial protection against specific losses, not a tool for routine performance measurement.
E. Force majeure: This is a contractual clause that excuses a party from liability for non-performance due to extraordinary, uncontrollable events.
F. Justification: This is an explanation provided during a performance review process, not a foundational structural component of the management framework itself.
1. CIPS (Chartered Institute of Procurement & Supply). (2018). L4M3 Commercial Contracting Study Guide. Profex Publishing.
Chapter 7
Section 1
'Key performance indicators (KPIs)': This section details the necessity of KPIs as the primary tool for measuring supplier performance against contractual obligations.
Chapter 7
Section 2
'Setting performance targets': This part explains that targets are essential benchmarks against which KPI data is compared to determine success or failure.
Chapter 7
Section 4
'Remedies for non-performance': This section discusses various actions (consequences) that can be taken in response to poor performance
such as service credits or termination
which are integral to a performance framework.
2. Gordon
S. R. (2008). Supplier Evaluation and Performance Excellence: A Guide to Meaningful Metrics and Successful Results. J. Ross Publishing.
Chapter 4
'The Performance Measurement Process': This chapter outlines the essential steps
stating
"The process begins with defining what to measure (KPIs)
setting performance goals (targets)
and establishing a system for rewards and recognition or corrective action (consequences)." (Paraphrased from concepts on pp. 55-61).
3. Monczka
R. M.
Handfield
R. B.
Giunipero
L. C.
& Patterson
J. L. (2016). Purchasing and Supply Chain Management (6th ed.). Cengage Learning.
Chapter 14
'Supplier Performance Management': The text describes a comprehensive supplier measurement and management system as including metrics (KPIs)
standards (Targets)
and a systematic process for addressing performance that falls short
which implies consequences (pp. 510-515).
Keep practicing
Take the free L4M3 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other L4M3 practice questions
- Question 1A tire manufacturer entered into a contract with a distributor. In the contract, the dist…
- Question 2To expand its operation, Steel Co. decides to build a new plant. Despite of excitement, t…
- Question 3Which of the following are most likely to be substantive elements of the specification of…
- Question 4Michelle contacts Hannah and asks her if she would be interested in purchasing her car fo…
- Question 5Which of the following statements is FALSE on contracts for the leasing of assets?
- Question 6You are to do the KPIs and targets for international supplier and the following was done …