L4M4 practice question 23 of 25
A business may be faced with the challenge of deciding whether to source some of its requirements from external suppliers or whether to make them internally. Which of the following factors is likely to justify the decision to make the requirements internally?
Full set: 293 questionsThe 'make-or-buy' decision is a strategic choice based on a thorough analysis of costs, risks, and capabilities. A primary justification for the 'make' decision is the internal availability of the necessary resources. This includes having employees with the right skills and expertise (competencies) and having the machinery, facilities, and time available to undertake the production without disrupting other core activities (capacity). Without both in-house competency and capacity, the 'make' option is not viable, regardless of other factors.
A. Suppliers using older technology is a weak justification unless the buying firm possesses superior technology and can leverage it effectively.
C. Suspicions of overcharging should be verified through market analysis or negotiation, not used as a sole reason for insourcing.
D. Avoiding cumbersome procedures is a poor strategic reason; the internal costs and complexity of 'making' are often far greater.
1. Baily, P., Farmer, D., Jessop, D., & Jones, D. (2015). Procurement, Principles & Management (11th ed.). Pearson Education. Chapter 9, 'Make or Buy', pp. 182-184. (Lists 'availability of production capacity' and 'possession of the requisite skills and processes' as key factors favouring a 'make' decision).
2. Lysons, K., & Farrington, B. (2020). Procurement and Supply Chain Management (10th ed.). Pearson. Chapter 9, 'Make-or-Buy', p. 271. (Highlights that a reason to make is to 'utilise spare capacity and/or maintain a loyal, skilled workforce').
3. Monczka, R. M., Handfield, R. B., Giunipero, L. C., & Patterson, J. L. (2016). Purchasing and Supply Chain Management (6th ed.). Cengage Learning. Chapter 7, 'Make or Buy, Insourcing, and Outsourcing', p. 229. (Identifies 'availability of capable suppliers' and 'sufficient internal capacity' as critical considerations).
Keep practicing
Take the free L4M4 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other L4M4 practice questions
- Question 1What is the best way to prevent potential issues of conflicts of interest?
- Question 2Which of the following incoterms has the lowest risk to the buyer?
- Question 3What is a major benefit to using Incoterms when sourcing goods internationally?
- Question 4When using a 'credit account' payment mechanism, when does a supplier receive payment for…
- Question 5Which of the following are examples of secondary data? Select TWO
- Question 6A procurement manager has a new contract to award. They know there will be considerable i…