L4M4 practice question 24 of 25
In the Public Sector, what is the evaluation criteria most often used when evaluating bids from suppliers?
Full set: 293 questionsIn public sector procurement, regulations mandate fairness, transparency, and achieving value for money. The "Most Economically Advantageous Tender" (MEAT) is the specific criterion used to fulfill these obligations. MEAT allows the contracting authority to evaluate bids based on a combination of price and other quality-related criteria (e.g., technical merit, environmental characteristics, service levels). This ensures the chosen bid represents the best overall value, not just the lowest price, which is a key principle of public spending.
B. Best Value for Money: This is the overarching principle or goal, but MEAT is the specific evaluation methodology or criterion used to achieve it in a tender process.
C. Cheapest Overall Tender: This criterion (lowest price) is permissible but less common for complex procurements, as it ignores quality and can lead to poor long-term outcomes.
D. Best Business Fit: This term is more subjective and commonly used in the private sector; public procurement requires more explicit, objective, and pre-defined criteria like MEAT.
- The Public Contracts Regulations 2015, SI 2015/102, Part 2, Chapter 3, Section 6, Regulation 67, "Contract award criteria." This UK legislation explicitly states that contracts shall be awarded on the basis of the most economically advantageous tender.
- European Commission. (n.d.). Public procurement. "Awarding contracts." The official guidance on EU directives (which form the basis of CIPS curriculum on this topic) specifies that the award criterion is either the lowest price or the most economically advantageous tender (MEAT).
- CIPS. (2021). Sourcing in Procurement and Supply (L4M4). Profex Publishing. Chapter 5, "Evaluating Tenders," details the MEAT criterion as central to public sector tender evaluation.
Keep practicing
Take the free L4M4 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other L4M4 practice questions
- Question 1What is the best way to prevent potential issues of conflicts of interest?
- Question 2Which of the following incoterms has the lowest risk to the buyer?
- Question 3What is a major benefit to using Incoterms when sourcing goods internationally?
- Question 4When using a 'credit account' payment mechanism, when does a supplier receive payment for…
- Question 5Which of the following are examples of secondary data? Select TWO
- Question 6A procurement manager has a new contract to award. They know there will be considerable i…