L5M6 practice question 4 of 15
What is contract leakage?
Full set: 92 questionsContract leakage, often termed 'value leakage,' refers to the erosion of value from a contract throughout its lifecycle. It represents the difference between the potential benefits and savings identified in the business case or pre-award negotiation stage and the actual value that is realized post-award. This gap can arise from various factors, including poor supplier performance, failure to claim credits or rebates, maverick spending outside the agreed terms, and inefficient contract management processes. The concept encompasses all forms of lost value, not just financial overspend.
A. This describes a budget overrun or overspending. While this can be a component of contract leakage, it is not the complete definition of the concept.
B. This describes underspending against a forecast. This is not leakage and could potentially be a positive outcome if achieved through genuine efficiencies.
C. This describes a performance gap. Poor performance against Key Performance Indicators (KPIs) is a significant cause of value leakage, but it is a symptom, not the definition itself.
1. World Commerce & Contracting (formerly IACCM). The concept of value leakage is central to the research conducted by WorldCC. Their studies consistently find that poor contract management leads to an average value leakage of 9% of the contract's annual value. This leakage is defined as the failure to realize the full potential value of a negotiated agreement.
Source: World Commerce & Contracting, "The Business Case for Contract Management," (various reports, e.g., 2017/2019). The reports detail how this 9% leakage is the gap between the negotiated business case and the realized outcomes.
2. Gelderman, C. J., Semeijn, J., & Vluggen, R. (2017). "The impact of the procurement function’s involvement on value creation in a public-private partnership." Journal of Purchasing & Supply Management, 23(3), pp. 179-191.
Reference: This article discusses value creation and appropriation in complex contracts. It implicitly supports the definition of leakage by highlighting the challenges in realizing the intended value (p. 180, Section 2.2 on Value Creation), which is the core of the leakage concept. The gap between ex-ante (expected) and ex-post (realized) value is the essence of leakage. DOI: https://doi.org/10.1016/j.pursup.2017.04.002
3. University of Tennessee, "Vested Outsourcing: Five Rules That Will Transform Outsourcing" (Courseware/White Paper).
Reference: The Vested methodology, developed at the University of Tennessee, focuses on creating outcome-based agreements designed to minimize value leakage. The core principle is to align the parties' interests to ensure the intended value of the business case is achieved in practice, directly addressing the gap described in option D. (See "Creating a Win-Win Vested Agreement," White Paper, UT Center for Executive Education).
Keep practicing
Take the free L5M6 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other L5M6 practice questions
- Question 1According to studies completed by Reeves, Moose and Venema in 2014, which of the followin…
- Question 2A 'should cost' analysis and value analysis can be completed on items procured by a buyer…
- Question 3What can the IACCM help a Category Manager with?
- Question 5Which category of spend item would be most suitable to purchase through an e-auction?
- Question 6Teddy Ltd has created a virtual cross-functional procurement team across divisions. What …
- Question 7SIC codes are sets of four-digit codes used to classify what?