L6M5 practice question 3 of 15

When is the best time to define acceptance criteria for a project? Answer Options:

Full set: 83 questions
Answer options
A: Upon completion
B: During each milestone
C: When writing the Project Initiation Document Correct answer
D: As part of the Project Audit
Correct Answer:
C. When writing the Project Initiation Document
Explanation

Acceptance Criteria should be set before the project starts in the Project Initiation Document (PID) (p.137).
Option A is too late, as the project is already completed.
Option B is iterative, but criteria should be predefined.
Option D is for evaluation, not definition. [P.137]