LEED-AP-HOMES practice question 28 of 35

A builder plans to build two semi-detached residential homes at a rural lot he just bought, where the municipal water system cannot reach. The homes will use well water dug on site. The builder would like to build the two units as LEED certified homes. To meet the prerequisite of Water Efficiency domain in LEED Homes, what should the builder do?

Full set: 100 questions
Answer options
A: Install two water meters for each unit separately Correct answer
B: Use one water meter for the entire building of two units
C: These two semi-detached homes will be exempt from the prerequisite of Water Efficiency
D: At least one water meter will be shared by two units, and another separate meter will be used for monitoring landscaping water usage
Correct Answer:
A. Install two water meters for each unit separately
Explanation

The LEED for Homes v4 WE Prerequisite: Water Metering requires projects with multiple dwelling units to provide consumption feedback to occupants. For a project with two semi-detached homes, this is achieved by installing a separate water meter for each individual unit. This allows each homeowner to monitor and manage their specific water usage, which is a core intent of the prerequisite. The source of the water, whether municipal or a private well, does not alter this requirement; all potable water entering the dwelling must be metered.

Why Incorrect

B. A single meter for both units does not provide individual consumption data to each homeowner, failing to meet the prerequisite's intent for multi-unit projects.
C. The use of on-site well water does not exempt a project from the Water Efficiency prerequisites. The requirement to meter potable water use remains applicable.
D. A shared meter for the dwelling units is insufficient. The prerequisite mandates individual metering for each unit in a multi-family configuration to encourage occupant-level conservation.

References

1. U.S. Green Building Council. (2016). LEED Reference Guide for Homes Design and Construction, v4. Washington, DC: U.S. Green Building Council. Page 337, WE Prerequisite Water Metering, Requirements, "For Multiple dwelling units": "Install a water meter for each individual dwelling unit." or "Install a building-level water meter and submeter at least 80% of the dwelling units." For a two-unit project, 80% requires submetering both units, making the outcome identical to the first option.

2. U.S. Green Building Council. (2021). LEED v4.1 Homes and Multifamily. USGBC.org. WE Prerequisite Water Metering section, which maintains the requirement for individual dwelling unit metering in multifamily projects to provide data to tenants or owners.