LEED-AP-HOMES practice question 17 of 35
Looking at the attached table, a project team is aiming for three points in Water Efficiency Credit, Outdoor Water Use. The site contains a total of…
Choose your answer, then check it against the explanation.
Looking at the attached table, a project team is aiming for three points in Water Efficiency Credit,
Outdoor Water Use. The site contains a total of 57,500 ft² (5,342 m²) of softscape. If the plan has
8,000 ft² (743 m²) of turf grass, what is the minimum area of native or adapted landscape required to
achieve the desired three points for this credit?
Turf grass area Native or adapted plant area
Points
25%
1
50%
2
75%
3
75%
4
Question 17 of 35
Keep practicing
Take the free LEED-AP-HOMES practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other LEED-AP-HOMES practice questions
- Question 1For a typical single-family home, plumbing fixtures may account for what fraction of the …
- Question 2A LEED for Homes project is located in an area heavily infested with termites. A project …
- Question 3A project has a 2,500 ft² (232 m²) roof, 200 ft² (18.58 m²) uncovered patio, 100 ft² (9 m…
- Question 4Who of the following may submit to Green Business Certification Inc. a LEED for Homes pro…
- Question 5To comply with Materials and Resources Prerequisite: Certified Tropical Wood, all wood in…
- Question 6A project team targets concrete as a material to receive Environmentally Preferable Produ…