Key functional and operational parameters such as occupied hours of a building, use by space type, required temperature settings, and lighting levels, are specified in the
Full set: 168 questionsThe Owner Project Requirements (OPR) is a document that details the ideas, concepts, and criteria determined by the owner to be important to the success of the project. It typically includes key functional and operational parameters such as occupied hours of a building, use by space type, required temperature settings, and lighting levels. The OPR is used as a guiding document throughout the design and construction process to ensure that the team is aligned with the owner’s vision and goals.
Reference: LEED v4: Building Operations + Maintenance Guide, Functional / Operational | WBDG - Whole Building Design Guide, Facilities Operations & Maintenance - An Overview - WBDG The Owner Project Requirements (OPR) is a critical document that outlines the functional and operational objectives of a project, reflecting the owner's needs and expectations. This document serves as a foundation for the design team to develop the Basis of Design (BOD) and guides the project through its lifecycle, ensuring that the owner's operational needs, such as occupied hours, use by space type, required temperature settings, and lighting levels, are met. The OPR typically includes information on building occupancy schedules, space usage types, environmental conditions like temperature and lighting requirements, and other owner-driven criteria essential for the building's design and operation. By clearly defining these parameters upfront, the OPR ensures that the project team has a clear understanding of what is expected from the building's performance, facilitating a design that aligns with the owner's vision and operational needs.
Reference: Based on the LEED AP documents and resources, such as the ASHRAE 90.1-2013 User Manual, which provides guidelines for determining design and operational parameters like lighting wattage for various space types (ASHRAE 90.1-2013, Section 9.1.4) .
Keep practicing
Take the free LEED-AP-OM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other LEED-AP-OM practice questions
- Question 1For an office building with few visitors, which of the following actions must the project…
- Question 2Which of the following is the most appropriate use of untreated stormwater?
- Question 3How is the energy baseline determined in Minimum Energy Performance if the building type …
- Question 4An ASHRAE Level 1 walkthrough analysis contributes to what prerequisite or credit?
- Question 5Under Indoor Environmental Quality Credit, Interior Lighting, outlet powered task lightin…