LEED-AP-OM practice question 24 of 25

Which of the following people are required to be listed on the LEED project registration page?

Full set: 168 questions
Answer options
A: Owner Correct answer
B: LEED AP
C: Primary Architect
D: Commissioning (Cx) agent
Correct Answer:
A. Owner
Explanation

The owner is the only person who is required to be listed on the LEED project registration page. The owner is the entity that has the authority to implement the LEED project and sign the certification agreement. The owner’s representative, who can be a LEED AP or another person authorized by the owner, can register the project on behalf of the owner, but must also upload a confirmation of agent authority form. The primary architect, the commissioning agent, and other project team members are not required to be listed on the registration page, but can be added later as team members in LEED Online.
Reference: Registering a project in LEED Online LEED AP O+M Candidate Handbook, page 7