A manufacturing company uses master planning in Dynamics 365 Supply Chain Management. Purchase orders for a raw material are created more frequently…

Full set: 195 questions

Domain Implement and manage planning

A manufacturing company uses master planning in Dynamics 365 Supply Chain Management. Purchase orders for a raw material are created more frequently than needed. This results in missed discounts with the vendor who sells the raw material. The raw material items have a 30-day lead time. The company is willing to delay sales and production order demand that may consume the raw material for up to 15 days to consolidate purchase orders. You need to configure the setup to include lead time and consolidate purchase orders. What should you configure?
Answer options
A: negative days only
B: positive days
C: dynamic negative days and negative days Correct answer
D: dynamic negative days only
Correct Answer:
C. dynamic negative days and negative days
Explanation

The goal is to consolidate purchase orders by delaying demand fulfillment and considering the item's lead time. This requires configuring two specific master planning parameters:
1. Negative days: This setting directly addresses the company's willingness to delay demand. Setting this to 15 days tells the master planning engine that it is acceptable to use a supply order (like an existing purchase order) that arrives up to 15 days after the demand date, thus preventing the creation of a new, separate order.
2. Dynamic negative days: This setting instructs master planning to use the item's lead time (30 days in this case) as the negative days period. This prevents the system from creating a new purchase order for a demand when an existing one is already scheduled to arrive within the lead time. When both are configured, the system uses the longer of the two periods. This combination provides the most robust solution for consolidating orders by using existing supply within the lead time and explicitly allowing for a specified delay.

Why Incorrect

A. negative days only: This is insufficient because it ignores the long lead time. The system would not be able to use an existing purchase order arriving in 20 days to fulfill a demand if negative days were only set to 15.
B. positive days: This setting looks forward for surplus inventory to use for new demand. It does not allow for delaying demand fulfillment, which is a key requirement of the scenario.
D. dynamic negative days only: While this considers the lead time, it does not explicitly capture the business rule of being willing to delay demand for "up to 15 days." Configuring both settings ensures all business constraints are modeled.

References

1. Microsoft Learn. (2023). Coverage settings. In Dynamics 365 Supply Chain Management documentation.

Section: "Negative days" and "Dynamic negative days".

Content: The documentation states

"The negative days represent the number of days that you're willing to delay a demand." It further explains

"If you select the Dynamic negative days check box

the system uses the longer of the two periods: the item's lead time or the value in the Negative days field." This confirms that configuring both is the correct approach to model the scenario's requirements for both an acceptable delay and consideration of the lead time.

2. Microsoft Learn. (2023). Master planning with demand forecasts. In Dynamics 365 Supply Chain Management documentation.

Section: "Time fences".

Content: This section details how time fences

including negative days

are used by the master planning engine to make decisions about supply orders. It reinforces that negative days are the primary tool for allowing demand to be fulfilled late by existing or consolidated supply

which is the core of the question.

Scroll to Top