MB-335 practice question 9 of 25

You are a process engineer evaluating lean vs. Discrete processing. You warn to convert a Kanban item. This item has the following Lean setup: • The…

Full set: 195 questions

Domain Implement and manage manufacturing

You are a process engineer evaluating lean vs. Discrete processing. You warn to convert a Kanban item. This item has the following Lean setup: • The setup uses a lean schedule group with a throughput ratio = 2. • The process activity tied to production flow has the following runtime activity times: time = 3 mm. per quantity = 1. • The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8-hour day). • The throughput is 10 per hour. You need to set up a Discrete operation to mirror the item s production flow activity. What should you do?
Answer options
A: Create a route with a runtime = 1, a process quantity = 10. and the operation's hours/time = 1.
B: Create a route with a runtime - 6, a process quantity- 1, and the operation's hours/time - 1. Correct answer
C: Create a route with a runtime = 10. a process quantity = 6. and the operation's hours/time= 1.
D: Create a route with a runtime = 1. a process quantity = 1, and the operation's hours/time = 1.
Correct Answer:
B. Create a route with a runtime - 6, a process quantity- 1, and the operation's hours/time - 1.
Explanation

The objective is to configure a discrete route that mirrors the effective cycle time of the lean setup. The lean activity's standard time is 3 minutes per piece. The lean schedule group's throughput ratio of 2 is a multiplier applied to the standard time to determine the effective cycle time for scheduling. Effective Cycle Time = Standard Activity Time × Throughput Ratio Effective Cycle Time = 3 minutes/piece × 2 = 6 minutes/piece. This means the work cell is scheduled to take 6 minutes to produce 1 piece. To mirror this in a discrete route, the operation must reflect this rate. Option B sets a runtime of 6 for a process quantity of 1, directly matching the calculated parameters.

Why Incorrect

A. While this option represents the correct rate (1 hour for 10 pieces = 6 minutes/piece), a process quantity of 1 more accurately mirrors a single-piece flow lean activity.
C. This represents a rate of 6 pieces per 10 hours (100 minutes per piece), which is an incorrect production rate based on the provided lean setup.
D. This represents a rate of 1 piece per hour (60 minutes per piece), which is an incorrect production rate based on the provided lean setup.

References

1. Microsoft Learn. (2023). Set up a lean schedule group. In Dynamics 365 Supply Chain Management documentation.

Reference: Under the "Fields" section for the "Lean schedule groups" page

the documentation for the Throughput ratio field states: "Enter a factor to multiply with the cycle time that is calculated from the production flow activity times. The result is the effective cycle time that is used to load the work cell." This supports the core calculation used to determine the correct answer.

2. Microsoft Learn. (2023). Routes and operations. In Dynamics 365 Supply Chain Management documentation.

Reference: In the section "Route operations

" the documentation explains that Run time is the time required to produce the specified Process quantity. This confirms that the route must be set up to reflect the calculated time per quantity (6 minutes per 1 piece).

3. Microsoft Learn. (2023). Production flow models. In Dynamics 365 Supply Chain Management documentation.

Reference: The section "Activity-based production flow models" describes how activity times are the basis for calculating cycle times in a lean production flow

which is the starting point for the calculation in this question.

Scroll to Top