MB-335 practice question 9 of 25

You are a process engineer evaluating lean vs. Discrete processing. You warn to convert a Kanban item. This item has the following Lean setup: • The…

Choose your answer, then check it against the explanation.

You are a process engineer evaluating lean vs. Discrete processing. You warn to convert a Kanban item. This item has the following Lean setup: • The setup uses a lean schedule group with a throughput ratio = 2. • The process activity tied to production flow has the following runtime activity times: time = 3 mm. per quantity = 1. • The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8-hour day). • The throughput is 10 per hour. You need to set up a Discrete operation to mirror the item s production flow activity. What should you do?
Answer options
Question 9 of 25

Keep practicing

Take the free MB-335 practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other MB-335 practice questions

Scroll to Top