MB-335 practice question 9 of 25
You are a process engineer evaluating lean vs. Discrete processing. You warn to convert a Kanban item. This item has the following Lean setup: • The…
Full set: 195 questionsDomain Implement and manage manufacturing
The objective is to configure a discrete route that mirrors the effective cycle time of the lean setup. The lean activity's standard time is 3 minutes per piece. The lean schedule group's throughput ratio of 2 is a multiplier applied to the standard time to determine the effective cycle time for scheduling. Effective Cycle Time = Standard Activity Time × Throughput Ratio Effective Cycle Time = 3 minutes/piece × 2 = 6 minutes/piece. This means the work cell is scheduled to take 6 minutes to produce 1 piece. To mirror this in a discrete route, the operation must reflect this rate. Option B sets a runtime of 6 for a process quantity of 1, directly matching the calculated parameters.
A. While this option represents the correct rate (1 hour for 10 pieces = 6 minutes/piece), a process quantity of 1 more accurately mirrors a single-piece flow lean activity.
C. This represents a rate of 6 pieces per 10 hours (100 minutes per piece), which is an incorrect production rate based on the provided lean setup.
D. This represents a rate of 1 piece per hour (60 minutes per piece), which is an incorrect production rate based on the provided lean setup.
1. Microsoft Learn. (2023). Set up a lean schedule group. In Dynamics 365 Supply Chain Management documentation.
Reference: Under the "Fields" section for the "Lean schedule groups" page
the documentation for the Throughput ratio field states: "Enter a factor to multiply with the cycle time that is calculated from the production flow activity times. The result is the effective cycle time that is used to load the work cell." This supports the core calculation used to determine the correct answer.
2. Microsoft Learn. (2023). Routes and operations. In Dynamics 365 Supply Chain Management documentation.
Reference: In the section "Route operations
" the documentation explains that Run time is the time required to produce the specified Process quantity. This confirms that the route must be set up to reflect the calculated time per quantity (6 minutes per 1 piece).
3. Microsoft Learn. (2023). Production flow models. In Dynamics 365 Supply Chain Management documentation.
Reference: The section "Activity-based production flow models" describes how activity times are the basis for calculating cycle times in a lean production flow
which is the starting point for the calculation in this question.
Keep practicing
Take the free MB-335 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other MB-335 practice questions
- Question 1Note: This question is part of a series of questions that present the same scenario. Each…
- Question 2You are responsible for product and formula maintenance for a paint manufacturer. You cre…
- Question 3A manufacturing company uses master planning in Dynamics 365 Supply Chain Management. Pur…
- Question 4A company uses Dynamics 365 Supply Chain Management. A piece of machinery that is critica…
- Question 7Note: This question is part of a series of questions that present the same scenario. Each…