MOVF practice question 14 of 35

Which is a true statement about the Value Index?

Full set: 100 questions
Answer options
A: It is a measure of how well the project, in its current state of development, satisfies the project objectives Correct answer
B: It measures value for money
C: It is based on non-financial criteria
D: It should only be changed if business needs change
Correct Answer:
A. It is a measure of how well the project, in its current state of development, satisfies the project objectives
Explanation

The MoV® Guide defines the Value Index as “a measure, at a point in time, of how well the solution under consideration would meet the project’s objectives.” It compares the forecast contribution of the current design to the agreed objectives and is recalculated as the solution evolves. The metric therefore provides management with an immediate view of whether the emerging solution is still on track to deliver the required outcomes, independent of whether costs represent “value for money” or whether the business needs themselves have changed.

Why Incorrect

B. Focuses on cost–benefit (“value for money”); the Value Index is objective-achievement, not cost efficiency.
C. Index combines whatever criteria are in the Objectives hierarchy, many of which are financial; it is not limited to non-financial aspects.
D. The Index naturally changes as the design or cost profile changes, even when business needs remain constant.

References

1. Office of Government Commerce (OGC). “Management of Value (MoV®)”, TSO, 2010, Sect. 4.4, p. 100: para. 2 – definition of Value Index.

2. OGC MoV® Guide, App. A, p. 219 – explanation that Index is recalculated as options evolve, irrespective of changing needs.

3. D. Kelly, “Value Management in Design and Construction”, Routledge, 2016 (aligned with MoV principles), Ch. 6, pp. 118-119 – clarifies distinction between value-for-money metrics and objective-satisfaction indices.